Wednesday, September 29, 2010

Day 21 - 9/28/2010

Today was HVAC day.  The crew was back working on the downstairs HVAC unit.  The source and return plenums were replaced, all the ductwork was replaced and a new return was added on the west side of the house.

Silver ductwork running every which way... looks like something from a sci-fi movie... take us to WARP 3 Scotty.
Joseph brought some samples of baseboard and casing trim to pick from.  Not quite as much fun as selecting cabinets and granite... but it's gotta be done.

More inspections planned for Wed and a walk-through with Andy, Ryan and Pat to make sure everything that needs to be done before sheet rocking is done.  It's a pain, not to mention, costly to fix things after closing up the walls.

Oh yea, we got the first invoices in from RHD... time to write a huge check!  They have done a LOT of work as you have seen on this blog and this is the first time that they have asked for some cold hard $$$.  Their accounts person has been on vacation, otherwise I'm sure they would have sent me some invoices sooner.  AWA's are supposed to be invoiced at the time of approval.

That was pretty much it for Monday.